(Source: University of Wyoming) July 1, 2016 - These are among the construction activities scheduled July 3-9 at the University of Wyoming: Campuswide (Big Horn Roofing, Laramie; November 2016) -- Campus roof replacements will occur in the following order, weather permitting: Fieldhouse roof is complete; Fieldhouse north addition roof replacements are 90 percent complete; mobilizing to Knight Hall, west-side rooms, restroom and roof over Registration and Records; Pharmacy, upper penthouse roofs; Animal Science, roofs over the meat lab and sales on the northwest side; RMMC, entry and front office area; Casper Family Practice, east-side addition. Use caution around equipment and work crews'...
↧